23 December 2026
- Sunday, 20 December 2026, day off
- Monday, 21 December 2026
- Tuesday, 22 December 2026
- Wednesday, 23 December 2026, due date
- Thursday, 24 December 2026
- Friday, 25 December 2026, day off
- Saturday, 26 December 2026, day off
Legal limit: by Friday, 22 January 2027 (60 days after 23 November 2026).
- 23 November 2026 Invoice date
- 23 December 2026 Due date
- 24 December 2026 Interest from
Line for your invoice (in Dutch):
Betalingstermijn: 30 dagen. Te betalen uiterlijk woensdag 23 december 2026.
If your customer does not pay on time, statutory commercial interest (wettelijke handelsrente) runs from Thursday, 24 December 2026. That is the interest the law gives for a business payment. The law applies it by itself. You do not need to send anything (art. 6:119a BW).
Counted from the invoice date. In law, the day of receipt counts. Basis: art. 6:119a lid 5 BW. Moving on to a working day: art. 1 en 2 Algemene termijnenwet. Law as at Monday, 26 October 2026.
How the sum works.
Three things to know before you calculate.
- Country and type of customer You choose the country and the type of customer first. The legal limit depends on both.
- The term counts from receipt The legal term counts from receipt. If the delivery came after the invoice, enter that date.
- What you get back You see the due date, the legal limit and when interest starts.
- Invoice received
- Due date with no agreement 30 days after receipt
- Limit for businesses 60 days after receipt
On this page
The legal term for each type of customer
| Type of customer | The Netherlands | Belgium |
|---|---|---|
| Consumer | No maximum what you agree applies | No maximum interest and costs only after a free reminder boek XIX WER |
| Business | 60 days above that, you can challenge it art. 6:119a lid 5 BW | 60 days above that, the agreement does not count art. 4 § 1 wet 2 augustus 2002 |
| Large business | 30 days above that, void (the agreement does not apply) art. 6:119a lid 6 BW | 60 days no separate rule: the limit for businesses applies art. 4 § 1 wet 2 augustus 2002 |
| Public authority | 30 days, or at most 60 for a special assignment above that, it drops back to the maximum art. 6:119b lid 5 BW | 30 days, or at most 60 for a special assignment above that, it drops back to the maximum art. 4 § 2 wet 2 augustus 2002 |
With no agreement, a business customer and a public authority have 30 days after receiving the invoice, in both countries.
In Belgium
In Belgium, 60 days is a hard limit, since 1 February 2022. Unlike in the Netherlands, large businesses have no separate rule. If you agree a longer term between businesses, that agreement does not count (the law says: deemed unwritten). The term with no agreement then applies: 30 days after receiving the invoice. Only a royal decree can change that for a sector.
Does the last day fall on a weekend or public holiday? Then the term ends on the next working day. In Belgium that also holds for a term you agree yourself (art. 1.7 § 4 BW). A term of two days or more has at least two working days (§ 5). The contract can say otherwise (§ 7).
Is your customer a consumer? Then book XIX of the Code of Economic Law (WER) applies. You may ask for interest and costs only after a free reminder and a waiting period of 14 days. For a reminder sent by post, that starts on working day 3 after sending.
You can work out when the waiting period for a consumer ends with when can I charge costs.
Questions about the legal payment term
Is 14 days a legal payment term?
No. 14 days is a term you agree yourself, and that is allowed. Between businesses, any agreement up to 60 days is valid. For a large business in the Netherlands the limit is 30. The law itself names 30 days, and that only applies if nothing was agreed. With a consumer, 14 days applies if you agree it, ideally before the job.
What is the legal payment term?
In the Netherlands and Belgium, with no agreement, it is 30 days after receiving the invoice. That holds if your customer is a business or a public authority. Between businesses you can agree up to 60 days. In the Netherlands a longer term can be challenged. In Belgium it does not count. If a large business buys from a freelancer or small business, the limit in the Netherlands is 30 days. For public authorities the norm is 30 days, the maximum 60.
How long do you legally have to pay an invoice?
If nothing was agreed and your customer is a business, it is 30 days. These count from the day after receiving the invoice. If your customer does not pay, statutory commercial interest (wettelijke handelsrente) runs from the day after that. You do not need to send a formal demand (aanmaning) for it. According to recent case law, a Dutch consumer is only late (in verzuim) after a written formal demand. It must give a reasonable time to pay (art. 6:82 BW).
Does the term run from the invoice date or receipt?
In law, from receipt. The legal term of 30 days starts the day after receiving the invoice. If the delivery came later, that date counts. If acceptance or inspection of the delivery was agreed, the term in the Netherlands only starts after that. In Belgium the inspection falls within the payment term. An agreed term runs from the date you agree, usually the invoice date. This tool counts from the invoice date. You enter a later receipt separately.
What if the due date falls on a weekend?
In Belgium the last day moves on to the next working day, also for an agreed term (art. 1.7 § 4 BW). In the Netherlands the Algemene termijnenwet (General Time Limits Act) only does that for a term set by law. An agreed date does not move. The 30 days with no agreement do move on in this tool. The law does not say so in so many words, but this way you never charge interest too early. An agreed date can fall on a weekend. Then it is good manners to use the next working day.
What is the legal payment term in Belgium?
With no agreement it is 30 calendar days after receiving the invoice (art. 4 § 1 wet 2 augustus 2002). Between businesses you can agree at most 60 calendar days. A longer clause does not count (deemed unwritten), and then 30 days applies again. Belgium has no separate rule for large businesses. For a consumer, book XIX WER applies: interest and costs only after a free reminder and a waiting period.
How to put the term on the invoice itself is explained in the payment term on your invoice.
Where these rules come from
Law as at Monday, 26 October 2026. The Netherlands: articles 6:119a and 6:119b of the Dutch Civil Code (BW) and the General Time Limits Act (Algemene termijnenwet). Belgium: the act of 2 August 2002. Also article 1.7 of book 1 of the Civil Code, and book XIX of the Code of Economic Law (WER). The public holidays are those of the app: the Algemene termijnenwet for the Netherlands, the statutory holidays for Belgium.
This page is explanation, not legal advice. The dates come from the same calendar and term rules as the app itself. If you are unsure about a real case, take it to a lawyer.
Let Vordero follow the due date
Vordero reads the due date of every invoice. Your reminders go out on time in your name, following your sequence.
5 invoices a month free, no credit card.
-
Reminders on the right day
You choose per step how many days after the due date it goes out. Each invoice gets at most one reminder a day.
-
Interest from the right moment
For a business customer, Vordero works out the interest from the day after the due date. If you agreed no payment term in advance, the due date is 30 days after receipt, if that is later. For a consumer, only after the deadline of the first free letter.
-
Sent when you say so
You connect your accounting package or import a list. A customer then only gets a reminder once you switch it on for them.